nterior - 180 view coming out
of the sanctuary; to the left is the main door of the
building; to it's right is entrance to the nursery, then hallway
to the class room/elevator/rear stair and back door; turning right
is to the kitchen.
Interior - 180 view of the
hallway; straight left is to the sanctuary; first opening to
the right is the door to the toddler's room; door to the class
room is next to the rear stair to Mezzanine; and far right is the
door to the building back (dry wall is 70% completed in the
hallway).
Interior - 180 view of the
sanctuary from the A/V control room (in the Mezzanine).
Interior - 180 view of the
future church library (South corner); the door on the left is
the emergency exit from the mezzanine (dry wall is about 20%
complete in the Mezzanine); far right is the view to the
sanctuary; entrance to A/V is via the library.
Interior - 180 view of the
other non-door room (North corner) in Mezzanine.
Far left is the view to the sanctuary. If you look closely you can
see the existing house from its the windows.
July 13, 2005- Day 102
from Groundbreaking
- Stucco installation in progress; Mezzanine HVAC ducting work in
progress; rough-in of the screen and wires of the ceiling
projector done -
Exterior - View of building from the West/parking
lot (Stucco installation in progress).
Exterior - View from building's NW corner, taken
from the patio of the existing building. (Stucco installation in
progress. It's a 1" thick cement wall with the
lath holding the cement. The lath sits between the weather
resistive barrier
and the cement. Once the cement is dry, it will be painted.)
Stucco installation - detailed
view (the first layer is plastered on the lath).
Exterior - View of building from
the SW (stucco installation in progress in the exterior wall
of the prayer room).
Interior - 180 view from
the SW wall of the new building's library, at the Mezzanine,
located right on top of the Kitchen (Mezzanine HVAC ducting
work in progress).
Interior - 180 view from the
ground floor SE corner of building, showing class room
that abuts the kitchen to the left, and the rear stair to the
Mezzanine to the right of this picture (HVAC ducting in progress).
Interior - 180 view of
sanctuary from the AV room (in Mezzanine); Note the middle of
the picture, showing rough-in of the screen and wires of the
ceiling projector is done.
Interior - 180 view of the
sanctuary from the kitchen's window (Middle SE corner of the
building).
July 6, 2005- Day 95
from Groundbreaking
Except for the stucco area,
almost all the entrance's exterior wall are done.
Prep for stucco installation is 98% done. Final stucco
installation is either late this week or early next week.
Exterior - View from the West,
entrance to the new building from the parking lot:
(To the left is the existing
house; the mudded area in the center of the picture will be the
shared courtyard between the new and existing buildings; remaining
work on the west exterior face of the building is stucco
installation.)
Exterior - View from
the NW corner of the building
Exterior - Prep for stucco
installation (Zoomed in, showing two layers,
inner weather resistive barrier and an outer metal net layers
before stucco.)
Interior - 180°
view from
the Mezzanine's North corner facing the AV room
(Sanctuary is to
the right; Mezzanine's framing is 99% done; HVAC's ducting and the
electrical wiring work is progress before dry wall installation.)
Interior - 180° view near the sanctuary's
North exit door next to the storage area (Like in the Mezzanine, once the HVAC's ducting and
the electrical wiring are done, dry walling and ceiling tile
installation will be the next.)
June 30, 2005- Day 89
from Groundbreaking
-Preparing for stucco
installation; Heating, Ventilation, & Air Conditioning (HVAC) in
progress (return and fresh air ducting to
the sanctuary about 70% complete);
Dry wall (sheet rock) installation is next after
electric/plumbing; Soffit
(the underside)
of
the ceiling is complete-
Exterior - Building entrance/courtyard view from balcony of
existing house, looking at the NE side of the building
(preparing for stucco installation)
Exterior - Building view from
the West (Cedar Hills Blvd.)
Exterior - Detail of the weather
resistive barrier:
Interior - View from the
sanctuary toward the Hallway entrance/kitchen/class rooms
(facing SE), showing HVAC installation of return air vent on both
sides (by the windows)
Interior - View from the Hallway
(left is toward the rear mezzanine stairs/rear building exit,
and right is to the sanctuary entrance)
Interior - 180 degree view
from the mezzanine's south room/library; wall partition 80%
done; dry wall (sheet rock) installation next after
electric/plumbing
Interior
- 180 degree view of the sanctuary from mezzanine's AV room;
return and
fresh air ducting to the sanctuary about 70% completed; soffit at
both ceiling sides completed
June
22, 2005: Day 81 from Groundbreaking
- Most work from now on occurs
inside of the building: Heating, Ventilation, & Air Conditioning
(HVAC) started; ground floor/mezzanine partitioning and insulation
installation about 80% completed; fire sprinkler system
installation has also started; sheet rocking expected to begin
late next week or early the week of the July 4th. From the
outside, stucco (wall plaster) installation will start next week -
Interior - View from meeting hall
toward the building entrance hallway, kitchen and Mezzanine:
View toward building entrance from
the 2nd floor balcony of existing house (stucco installation will
start next week):
Interior - 180 View from Mezzanine's NW corner (on
left is a class room, in the middle is the A/V room, and the right
shows the meeting hall):
Interior - 180 View from building's entrance
(from left is baby room, middle the entrance hallway, and right
is the meeting hall
Exterior - View from building's SW corner
(prayer room's exterior stucco installation begins next week)
June
15, 2005: Day 74 from Groundbreaking
-Roof
done, stucco and metal installation in process, mezzanine level
construction has just begun-
View from Cedar Hills
Blvd (the existing house to the NNE Side, and the parking lot)
Interior
view from meeting hall facing SE toward hallway/Mezzanine (the
Mezzanine is being constructed)
Interior view from
meeting hall to hallway
Exterior of the Westside
of building
(Stucco installation over, the prayer room exterior is next)
Exterior of the Eastside of building
Interior
building from meeting hall facing SE toward hallway/Mezzanine
(roof insulation done. Mezzanine level construction next)
Interior - from back stairway facing hallway and
meeting hall entrance (the right side
is the class room next to the stairway to the Mezzanine)
June 8, 2005: Day 66 from Groundbreaking
-Roof
done, stucco and metal installation in process-
View from Cedar Hills Blvd (Showing
the existing house to the NNE Side)
Interior of new building
(View from the future meeting hall toward the
hallway/classroom/kitchen, with interior roof insulation 80%
complete, partitioning on the 1st floor with metal studs 40%
complete.)
View from hallway facing
the NW side toward the meeting hall (with interior roof
insulation 80% complete, partitioning on the 1st floor with metal
studs 60% complete)
View from new building's
West side - exterior metal siding completed except for stucco on
the prayer room:
View From 2nd floor balcony of the
existing house (facing new
building entrance - Roof done, and stucco and metal installation
in process)
June 1, 2005: Day 59 from Groundbreaking
Roof 90% installed, metal siding installation in progress
Interior - Facing the
future pulpit
Facing the Build entrance from Cedar Hills Blvd.
(NW side)
Facing the Build entrance
from Cedar Hills Blvd. (NW side) - Zoomed in
Toward the entrance of the
Building (walkway between the existing house and new building)
View from the 2nd floor
balcony of the existing house (facing SW)
Toward the entrance of
the Building - facing NW from SE
Building's West corner
facing the tennis recreation club (Metal siding ~40% completed on
this side)
May 25, 2005: Day 52 from Groundbreaking
Roof installation started -
Facing the Building from Cedar Hills Blvd. (NW side)
Inside the building -
Facing the SE Corner (the future pulpit)
Inside the building -
Facing Cedar Hills Blvd.
Going toward the
building entrance
View from the SE corner
(siding installation started)
Facing the NE corner
May 20, 2005: Day 47 from
Groundbreaking (4/4/05)
Photo 1
Photo 2
May 18, 2005: Day 45 from
Groundbreaking (4/4/05)
View from the NW side (current entrance)
View facing SW
View from the balcony of the existing house
View from building facing existing house
View from SW, facing Cedar Hill Blvd
May 16, 2005: Erection
Facing the future pulpit (podium):
Overview
Installing metal girder system
May 12, 2005: Steel Frame
Erection - Day 7
Panorama view from the southwest
of the building (front entrance of the lot)
Several different panorama views
of the building:
Photo 1
Photo 2
Photo 3
May 9, 2005: Erection/Girder
Overview
Girder01 (Installing
metal girder system)
May 6, 2005: Steel Frame
Erection
I. Steel Framing
Erected:
Photo 1
Photo 2
II. Sequence of frame erection:
Steel building shipped in, ready
to be erected
Frame transported by a fork-lift
Lifted up
Manually positioning
Installed on a footing
Releasing a hook from the erected frame
April 29, 2005: Concrete
poured and leveled in slab foundation form
Photo 1
Photo 2
Photo 3
April 27, 2005: Slab
Foundation Prepared for Rebar and Concrete Pour
Overview
Sand compacted with moisture barrier (black plastic)
Signs of Web Steel & Russell Construction
4-22-05 - Concrete
Footing/Elevator Pit
Overview
Concrete footings
Close-up of a concrete footing (w/ rebar)
Close-up of the elevator pit (worker removing outer forms)
4-20-05 - Forms of
Footing/Slab/Elevator Pit
Overview
Forms of footings
Close-up of the form of a footing (w/ rebar)
Close-up of the elevator pit (worker pumping out water)
4-18-05 - Footing
Excavation
Overview
Elevator Pit - now is like a
swimming pool
Footing excavation for steel frames (2'6" deep each)
4/12/05 - Rough-In (Electrical and
plumbing conduits are roughed-in before the pour of concrete):
photo 1
photo 2
4/9/05 - Fine-grading:
Gravels are placed in
trenches for fine-grading
Fine-grading continues
4/7/05 - Sub-grading:
Sub-grading is complete,
and fine-grading and trenching get started
Trenching begins in
the compacted building site
Trenching takes place
in the parking lot (PGE connection)
4/5/05 - Sub-grading:
A roller levels and
compacts piled gravels
Sub-grading continues
4/4/05 - groundbreaking:
photo 1
photo 2
photo 3